Press Release
WEIGHBRIDGE
NUMBER 2 PIER
Following
the decision at the March meeting to install a
new 50 Tonne capacity Weighbridge at Number 2
Pier, the Stornoway Port Authority Board at its
May meeting decided to look into the demolition
of the old concrete built Weighing Office and
replace it with a Glass Fibre Modular Type Building
.
This
was decided after consideration of a report by
Harbour Master Captain Torquil Macleod, which
pointed out that the existing building did not
offer a suitable option for housing the computer
and weighing software for the new Weighbridge.
The report pointed out that preliminary consultation
had already taken place with the Comhairle's Planning
Department to establish the best way ahead.
Subject
to agreement with the Planning Department as to
the type and materials to be used in the replacement
building, the Board approved of obtaining competitive
tenders for demolition of the old weighing office
and purchase of a modular building.
The
Board noted the further advantage of being able
to relocate a modular type building to another
site within the harbour should the Weigh Bridge
be relocated to the Number 1 Pier Area as part
of ongoing harbour improvements at a future date.
NUMBER
1 PIER LINKSPAN
Stornoway
Port Authority announces the award of a contract
to R J Macleod (Contractors) Ltd for the repair
to the steel piling of the Number 1 Pier Linkspan
Dolphin and the installation of a Cathodic Protection
(Anode) System, following a competitive tendering
process.
In
common with many other steel piled marine structures
in the UK , Stornoway's Number 1 Pier Linkspan
piling is suffering from Accelerated Low Water
Corrosion which has eaten into some of the sheet
piling and requires patching with new steel plates.
The
Port Authority decided that the continuing provision
of Number 1 Pier Linkspan was of high priority
when awarding the repairs contract amounting to
some £136,000 excluding Consultancy Fees
and Site Supervision costs.
Commenting
Chief Executive John J Maclennan said "It is vital
to have two Operational Linkspans at Stornoway,
not only to meet the needs of the two ferries
but also to provide essential back up in the event
of a linkspan having to be withdrawn from service
or closure of a berth for maintenance purposes.
Given
the usage of Number 1 Pier and Linkspan, the Authority
in the medium term aspires to replacing the existing
infrastructure with completely new facilities
should a funding opportunity arise".
DEBRIS
CLEARANCE: STORNOWAY HARBOUR
GLUMAIG BAY
Stornoway
Port Authority announces the award of a contract
for Debris Clearance from the Glumaig Bay / Arnish
Anchorage areas of the Harbour following receipt
of competitive tenders.
This
work was approved at a recent meeting of the Port
Authority Board following consideration of a report
by the Harbour Master Captain Torquil Macleod,
recommending that these areas be swept and cleaned.
The
Shetland based firm of Delta Marine Ltd is to
commence clearance work within the next week using
heavy "creeper" type gear designed principally
to locate and remove wire hawsers, old chains
etc. The cost of the operation which will last
for six days is in excess of £15,000.
Commenting
Chief Executive John J Maclennan said, "The Port
Authority incurred costs in excess of £50,000
clearing debris from the seabed in this important
Anchorage Area just over 3 years ago. Much of
the removed debris then consisted of old Trawl
Warps and it is anticipated that this clearance
operation will result in removing similar material,
some of which may have been dumped in the intervening
period.
The
Port Authority would again remind all Harbour
Users that the dumping of all litter at sea is
illegal and any persons found dumping Trawl Wires
or any other debris in the Harbour Limits will
be prosecuted. With the installation of digital
CCTV at Arnish Point there is now excellent surveillance
coverage in the Anchorages. We would appeal to
all users to stop the illegal practice of dumping
at sea."
The
Anchorages are used by a variety of vessels calling
at Stornoway, including the larger Cruise Liners
which are too big to berth alongside the main
Piers.