Press Release
Stornoway
Port Authority is pleased with progress to the
Fender Pile Repairs at the Town's Number 3 Pier
which required the closure of Number 3 Pier Ferry
Berth for the past two weeks, resulting in all
traffic and passengers having to use the old Number
1 Pier facility.
The
contract for repairs work in excess of £60k
was awarded to Aggregate Industries Ltd and involves
re-alignment work to damages on two piles caused
in separate incidents involving the MV Isle of
Lewis and MV Muirneag.
It
is anticipated that work will be completed in
the course of this week or early next week when
normal service at Number 3 Pier will be resumed.
Commenting,
Chief Executive, John J Maclennan said "The Authority
should like to thank all users and travelling
members of the public for their co-operation over
these weeks, and we would apologise for the inconvenience
caused.
Once
again this highlights the absolute necessity for
having two operational linkspans at Stornoway
so as to minimise disruption in the event of one
having to be withdrawn from service.
The
Board has recently incurred expenditure of approximately
£170k on steel repairs to the Number 1 Pier
Linkspan so as to secure its continued short term
use. However, taking a slightly longer view the
Port Authority considers that the only way ahead
is to rebuild Number 1 Pier and Linkspan in order
to meet the needs of the Island Community.
Following
a 10 years investment plan, nearing completion,
around the harbour at a cost of some £3.5M,
Mr. Maclennan confirmed that the next challenge,
of top priority facing the Board was the replacement
of Number 1 Pier and Linkspan and that he was
in the preliminary stages of investigating funding
opportunities with the relevant agencies".